Building project update

Week of December 18:

Excavation of the storm water management system continues. We did run into a little bit of rock this week but fortunately the contractor was able to jackhammer it out instead of blasting. Of course the jack hammering brings on additional costs but the costs should be relatively low. The storm water management pit will be filled in with stone and pipe during the next week after which the connection to the storm water system on Delp Road will occur. EG Stoltzfus is planning on submitting drawings to the township in the next two weeks.  This time frame for submission should enable them to begin construction on the addition by the end of January.

~ Andy Dula

4 photos from Dec.31, 2006
4 photos from Dec.24, 2006
7 photos from Dec. 19, 2006
Login Button
Page last modified 08/07/2008
Powered by Caravel CMS v3.4, Copyright © 2003-2008 Mennonite.net. All rights reserved.